Earned Value Management: Forecasting time
Controlling a project is key to the success or failure of the project. Earned Value Management (EVM) is a well-known technique to control the time and cost performance of a project and to predict the final project duration and cost. It is an easy tool to generate early warning signals to timely detect project problems or to exploit project opportunities. An overview of the EVM metrics is given in “Earned Value Management: An overview” and the formulas are summarized in “Earned Value Management: The EVM formulary”.
In “Earned Value Management: Forecasting project outcome”, it has been shown that the general forecasting formula for predicting the final duration, known as the Expected At Completion - Time (EAC(t)), is equal to:
- PF = 1: Future performance is expected to follow the baseline schedule.
- PF = SPI or SPI(t): Future performance is expected to follow the current time performance.
- PF = SCI or SCI(t): Future performance is expected to follow the current time and cost performance.
- Planned value method
- Earned duration method
- Earned schedule method
Forecasting method | Version 1: according to plan | Version 2: according to current time performance | Version 3: according to current time/cost performance |
Planned Value Method (PVM) | EAC(t)PV (PF = 1) | EAC(t)PV (PF = SPI) | EAC(t)PV (PF = SCI) |
Earned Duration Method (EDM) | EAC(t)ED (PF = 1) | EAC(t)ED (PF = SPI) | EAC(t)ED (PF = SCI) |
Earned Schedule Method (ESM) | EAC(t)ES (PF = 1) | EAC(t)ES (PF = SPI(t)) | EAC(t)ES (PF = SCI(t)) |
- Project progress is still early: if AT < PD then PD is used
- Project progress is already late: if AT > PD then AT is used
W1 | W2 | W3 | W4 | W5 | W6 | W7 | W8 | W9 | W10 | W11 | |
PV | 5.00 | 10.00 | 25.00 | 55.00 | 85.00 | 120.00 | 130.00 | 140.00 | 150.00 | 150.00 | 150.00 |
EV | 3.33 | 6.67 | 10.00 | 22.50 | 70.00 | 82.50 | 90.00 | 120.00 | 130.00 | 140.00 | 150.00 |
ES | 0.67 | 1.33 | 2.00 | 2.83 | 4.50 | 4.92 | 5.14 | 6.00 | 7.00 | 8.00 | 9.00 |
ED | 0.67 | 1.33 | 1.20 | 1.64 | 4.12 | 4.13 | 4.85 | 6.86 | 7.80 | 9.33 | 11.00 |
TV | -0.10 | -0.20 | -0.90 | -1.95 | -0.90 | -2.25 | -2.40 | -1.20 | -1.20 | -0.60 | 0.00 |
SPI | 0.67 | 0.67 | 0.40 | 0.41 | 0.82 | 0.69 | 0.69 | 0.86 | 0.87 | 0.93 | 1.00 |
SPI(t) | 0.67 | 0.67 | 0.67 | 0.71 | 0.90 | 0.82 | 0.73 | 0.75 | 0.78 | 0.80 | 0.82 |
CPI | 0.33 | 0.33 | 0.33 | 0.30 | 0.58 | 0.53 | 0.53 | 0.62 | 0.65 | 0.68 | 0.71 |
EAC(t)PV1 | 9.10 | 9.20 | 9.90 | 10.95 | 9.90 | 11.25 | 11.40 | 10.20 | 10.20 | 9.60 | 9.00 |
EAC(t)PV2 | 13.50 | 13.50 | 22.50 | 22.00 | 10.93 | 13.09 | 13.00 | 10.50 | 10.38 | 9.64 | 9.00 |
EAC(t)PV3 | 40.50 | 40.50 | 67.50 | 73.33 | 18.73 | 24.60 | 24.56 | 17.06 | 15.98 | 14.12 | 12.60 |
EAC(t)ED1 | 9.33 | 9.67 | 10.80 | 11.36 | 9.88 | 10.88 | 11.15 | 10.14 | 10.20 | 10.67 | 11.00 |
EAC(t)ED2 | 13.50 | 13.50 | 22.50 | 22.00 | 10.93 | 13.09 | 13.00 | 10.50 | 10.38 | 10.71 | 11.00 |
EAC(t)ED3 | 38.50 | 36.50 | 61.50 | 64.00 | 15.16 | 19.32 | 18.33 | 12.06 | 11.13 | 11.05 | 11.00 |
EAC(t)ES1 | 9.33 | 9.67 | 10.00 | 10.17 | 9.50 | 10.08 | 10.86 | 11.00 | 11.00 | 11.00 | 11.00 |
EAC(t)ES2 | 13.50 | 13.50 | 13.50 | 12.71 | 10.00 | 10.98 | 12.25 | 12.00 | 11.57 | 11.25 | 11.00 |
EAC(t)ES3 | 38.50 | 36.50 | 34.50 | 33.02 | 13.57 | 15.36 | 16.92 | 14.50 | 12.96 | 11.83 | 11.00 |
© OR-AS. PM Knowledge Center is made by OR-AS bvba | Contact us at info@or-as.be | Visit us at www.or-as.be | Follow us at @ORASTalks