Earned Value Management: The EVM formulary

Controlling a project is key to the success or failure of the project. Measuring the project performance along the life of the project is a way to provide early warning signals that can be used as triggers for corrective action in case the project is in danger. Earned Value Management (EVM) is a well-known technique to control the time and cost performance of a project. It is a methodology used since the 1960s, when the American Department of Defense proposed a standard method to measure a project's performance. The system relies on a set of often straightforward metrics to measure and evaluate the general health of a project. 

These metrics serve as early warning signals to timely detect project problems or to exploit project opportunities. This article gives an overview of the terminology used in EVM and in different articles published on www.pmknowledgecenter.com. Table 1 shows the main components of an EVM analysis, divided in four different layers. For an overview of the general EVM approach and references to further articles, see “Earned Value Management: An overview”.
 
Table 1: The different components of Earned Value Management
Name Meaning
Earned Value Management Key Parameters
S-curve
This graph displays the Planned Value (PV), the Actual Cost (AC) and Earned Value (EV) along the life of the project.
PV curve
This graph displays the Planned Value (PV) as shown in the S-curve. Since the Planned Value curve is available at the construction of the baseline schedule (before the EVM tracking), this graph is accessible separately from the S-curve.
Earned Schedule (ES)
This graph displays the Earned Schedule (ES) calculated from the Earned Value and Planned Value graph along the life of the project.
Project Performance
EVM Performance Dashboard This graph displays both the time and cost performance and divides the project performance into four regions showing time and cost performance.
Cost Variance (CV)
This graph displays the Cost Variance (CV = EV - AC) along the life of the project.
Cost Performance (CPI)
This graph displays the Cost Performance Index (CPI = EV / AC) along the life of the project.
Schedule Variance (SV and SV(t))
This graph displays the Schedule Variance (SV or SV(t)) along the life of the project. Formulas used: SV = EV - PV and SV(t) = ES - AT.
Schedule Performance (SPI and SPI(t))
This graph displays the Schedule Performance Index (SPI or SPI(t)) along the life of the project. Formulas used: SPI = EV / PV and SPI(t) = ES / AT.
Schedule Adherence (p-factor)
This graph displays how good the project progress follows the baseline schedule philosophy. This is known as schedule adherence and measured by the p-factor. Tip: p-factor = % schedule adherence (100% = perfect adherence).
Project Forecasting
Cost Estimate At Completion (EAC)
This graph displays the estimated final cost at project completion (EAC) predicted along the life of the project. Eight forecasting versions are used, in line with research from literature.
Time Estimate At Completion (EAC(t))
This graph displays the estimated final duration at project completion (EAC(t)) predicted along the life of the project. Three methods are used (PVM, EDM and ESM), each using three variants.
Forecast Accuracy
MAPE
This graph displays the Mean Absolute Percentage Error as a measure of the forecast accuracy of time or cost predictions.
MPE
This graph displays the Mean Percentage Error as a measure of the forecast accuracy of time or cost predictions.

© OR-AS. PM Knowledge Center is made by OR-AS bvba Contact us at info@or-as.beVisit us at www.or-as.beFollow us at @ORASTalks