Earned Value Management: Reliable time performance measurement
Controlling a project is key to the success or failure of the project. Earned Value Management (EVM) is a well-known technique to control the time and cost performance of a project and to predict the final project duration and cost. It is an easy tool to generate early warning signals to timely detect project problems or to exploit project opportunities. In “Earned Value Management: The three key metrics”, it has been discussed that EVM relies on three key input metrics, known as the planned value (PV), the actual cost (AC) and the earned value (EV). In “Measuring Time: Earned value or earned schedule?”, it has been shown that a fourth method, known as Earned Schedule (ES), works better for measuring the time progress of a project.
-
Schedule Variance (SV(t)): Shows the variance in time (ES - AT) expressed in time units
- > 0: project ahead of schedule
- = 0: project on time
- < 0: project delay
-
Schedule Performance Index (SPI(t)): Shows the performance of time (ES / AT) in a unitless dimension
- > 100%: project ahead of schedule
- = 100%: project on time
- < 100%: project delay
W1 | W2 | W3 | W4 | W5 | W6 | W7 | W8 | W9 | W10 | W11 | |
AT | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
PV | 5.00 | 10.00 | 25.00 | 55.00 | 85.00 | 120.00 | 130.00 | 140.00 | 150.00 | 150.00 | 150.00 |
AC | 10.00 | 20.00 | 30.00 | 75.00 | 120.00 | 155.00 | 170.00 | 195.00 | 200.00 | 205.00 | 210.00 |
EV | 3.33 | 6.67 | 10.00 | 22.50 | 70.00 | 82.50 | 90.00 | 120.00 | 130.00 | 140.00 | 150.00 |
ES | 0.67 | 1.33 | 2.00 | 2.83 | 4.50 | 4.92 | 5.14 | 6.00 | 7.00 | 8.00 | 9.00 |
SV | -1.67 | -3.33 | -15.00 | -32.50 | -15.00 | -37.50 | -40.00 | -20.00 | -20.00 | -10.00 | 0.00 |
SPI | 0.67 | 0.67 | 0.40 | 0.41 | 0.82 | 0.69 | 0.69 | 0.86 | 0.87 | 0.93 | 1.00 |
SV(t) | -0.33 | -0.67 | -1.00 | -1.17 | -0.50 | -1.08 | -1.86 | -2.00 | -2.00 | -2.00 | -2.00 |
SPI(t) | 0.67 | 0.67 | 0.67 | 0.71 | 0.90 | 0.82 | 0.73 | 0.75 | 0.78 | 0.80 | 0.82 |
- PV varies between € 0 (at the start of the project) and the budget at completion (BAC) at the end of the project.
- EV varies between € 0 (at the start of the project) and the budget at completion (BAC) at the end of the project.
- ES varies between 0 time units (at the start of the project) and the baseline Planned Duration (PD) at the end of the project.
- SV = EV - PV = BAC - BAC = 0 (when project is on time or late)
- SPI = EV / PV = BAC / BAC = 1 (when project is on time or late)
-
SV(t) = ES - AT = PD - AT
- > 0, if AT < ES (project is early)
- = 0, if AT = ES (project is on time)
- < 0, if AT > ES (project is late)
-
SPI(t) = ES / AT = PD / AT
- > 1, if AT < ES (project is early)
- = 1, if AT = ES (project is on time)
- < 1, if AT > ES (project is late)
© OR-AS. PM Knowledge Center is made by OR-AS bvba | Contact us at info@or-as.be | Visit us at www.or-as.be | Follow us at @ORASTalks